Summary

PRPL220219
Plumbing
Closed
JONES OUTPOST HOLDING LLC
New
New plumbing in kitchen including new floor drains, floor sinks, and new plumbing for hand sinks and dishwasher.
03/10/2022
03/18/2022
03/10/2025
02/18/2025

Locations

Submittals

1 Permit Application Submittal 03/10/2022      Status: Pending
Review Type Outcome Est. Completion Date Completed
Building Code Review VOID 03/24/2022 03/11/2022

Fees

There are no fees for this permit application, or you are not authorized to view them.

Inspections

Inspection Outcome Requested Scheduled Date Inspected
Plumbing Rough-in Inspection Partial Pass 3/11/2022 3/11/2022 03/11/2022
Silas Ebbert ((970) 870-5347)   Send Email
Plumbing Rough-in Inspection Partial Pass 3/21/2022 3/21/2022 03/21/2022
Jeff Yeiser ((970) 870-5371)   Send Email
Plumbing Rough-in Inspection Partial Pass 4/12/2022 4/12/2022 04/12/2022
Ron Norton ((970) 870-5331)   Send Email
Plumbing Rough-in Inspection Partial Pass 4/25/2022 04/25/2022
Silas Ebbert ((970) 870-5347)   Send Email
Plumbing Rough-in Inspection Passed 5/6/2022 5/6/2022 05/06/2022
Silas Ebbert ((970) 870-5347)   Send Email
Plumbing Final Inspection Partial Pass 5/20/2022 5/20/2022 05/20/2022
Ron Norton ((970) 870-5331)   Send Email
Plumbing Final Inspection Passed 9/6/2022 9/6/2022 09/06/2022
Silas Ebbert ((970) 870-5347)   Send Email
Approval for Gas Service VOID 02/18/2025
Tammy Green ((970) 870-5328)   Send Email

Conditions

There are no conditions for this permit application, or you are not authorized to view them.

Related Permit & Planning Applications

Reference Number Status Type
PREL220488 Closed Electrical

Documents & Images

Date Uploaded File Type Name
03/10/2022 Letter Permit - Detailed
03/11/2022 Report Inspection Report (Plumbing Rough-in Inspection)
03/21/2022 Report Inspection Report (Plumbing Rough-in Inspection)
04/12/2022 Report Inspection Report (Plumbing Rough-in Inspection)
04/25/2022 Report Inspection Report (Plumbing Rough-in Inspection)
05/06/2022 Report Inspection Report (Plumbing Rough-in Inspection)
05/20/2022 Report Inspection Report (Plumbing Final Inspection)