CityView Portal

Permit Application Status

PREL240088


You will only be able to schedule inspections if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PREL240088
Electrical
Closed
HAYDEN GRANARY, LLC
Addition
We have added a sub panel in the rear area. I'm likey out of town on Blues break. The property owner Patrick Delaney can show the pipe and sub panel in question OR my employee Morgan Biggart will be able to pe present if Patrick is unable
02/13/2024
02/14/2024
03/01/2024

Locations

Submittals

1 Permit Application Submittal 02/13/2024      Status: Pending
Review Type Outcome Est. Completion Date Completed
Electrical Review Approved 02/14/2024

Fees

There are no fees for this permit application, or you are not authorized to view them.

Inspections

Inspection Outcome Requested Scheduled Date Inspected
Electrical Rough-in Inspection Passed 2/16/2024 2/20/2024 02/20/2024
Tom Cook ((970) 870-5339)   Send Email
Electrical Final Inspection Partial Pass 2/16/2024 2/20/2024 02/20/2024
Tom Cook ((970) 870-5339)   Send Email
Electrical Underground/Underslab VOID 03/01/2024
Tom Cook ((970) 870-5339)   Send Email
Electrical Final Inspection Passed 03/01/2024
Tom Cook ((970) 870-5339)   Send Email

Conditions

There are no conditions for this permit application, or you are not authorized to view them.

Related Permit & Planning Applications

There are no related items for this permit application.

Documents & Images

Date Uploaded File Type Name
02/13/2024 Receipt Receipt for transaction:2024-000088
02/14/2024 Permit Permit - Detailed (Generate/Issue Permit(s) - Building)
02/20/2024 Report Inspection Report (Electrical Final Inspection)
02/20/2024 Report Inspection Report (Electrical Rough-in Inspection)
03/01/2024 Report Inspection Report (Electrical Final Inspection)