Permit Application Status

PRSF220380


You will only be able to schedule inspections if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRSF220380
New Single Family Dwelling
Permit(s) Issued
SOBESKI, LUKE & JAYME (JT)
New
R-3 - Residential, one- and two-family
50' x 50' Metal Building 1700sqft of Garage 800sqft of Living Space
04/19/2022
05/20/2022
05/20/2025

Locations

Submittals

1 Permit Application Submittal 04/19/2022      Status: Returned for Correction

Review Type Outcome Est. Completion Date Completed
Public Works Review Approved 05/04/2022 04/29/2022
Tony Brown ((970) 870-5344)   Send Email
Building Code Review Approved 05/04/2022 04/27/2022
Ted Allen ((970) 870-5329)   Send Email
GIS Land Development Review Approved 05/04/2022 04/27/2022
Jason Blair ((970) 870-5465)   Send Email
External Agencies Review Approved 05/04/2022 04/25/2022
Malea Michael-Ferrier ((970) 870-5334)   Send Email
YVEA - inspections@yvea.com Meter and meter pedestal are to be located as described by YVEA. They shall not be enclosed, covered or concealed. Violation shall result in termination of service. This approval addresses only the meter and service location. Steamboat Lake Water and Sanitation Powderhorn is not in our service area, so we do not have any comments. N. Routt Fire - chief@northrouttfire.org No issues or concerns with project. MS
Environmental Health Review Approved 05/04/2022 04/22/2022
Amanda Williams ((970) 870-5588)   Send Email
Planning Review Failed 05/04/2022 04/20/2022
Michael Fitz ((970) 879-2704)   Send Email
Miscellaneous
Carried Forward
05/16/2022


Property is skylined and a balloon test will be needed to determine compliance with skyline regulations.
Miscellaneous
Carried Forward
05/16/2022


Plat includes no-build zones on this lot. Please include them on the site plan so the position of the structure can be verified to be out of the no-build zones.
Proposal is for a single-family residence with large garage in a metal building in the MRE zone district. Property is >5 acres so a secondary unit is allowed in the future (under current regulations). 50' setbacks are met, 40' height is met, no waterbody or floodplain concerns exist. Site plan does not show no-build zones from the plat, and a balloon test is needed for skylining. No approval is implied for any future proposed work or dwelling units shown on this site plan.

2 Permit Application Submittal 05/02/2022      Status: Returned for Correction

Review Type Outcome Est. Completion Date Completed
Planning Review Failed 05/23/2022 05/16/2022
Michael Fitz ((970) 879-2704)   Send Email
Miscellaneous
Carried Forward
05/19/2022


Property is skylined and a balloon test will be needed to determine compliance with skyline regulations.
Miscellaneous
Resolved
05/16/2022


Plat includes no-build zones on this lot. Please include them on the site plan so the position of the structure can be verified to be out of the no-build zones.
Site plan now includes no-build zones, so that correction is resolved. Cannot approve until skyline test is conducted and compliance verified (test has been scheduled).

3 Permit Application Submittal 05/17/2022      Status: Pending

Review Type Outcome Est. Completion Date Completed
Building Code Review Approved 10/28/2022 10/24/2022
Ted Allen ((970) 870-5329)   Send Email
Addendum document received 10/19/2022 is conditionally approved; The garage shall be separated from the residence and its attic area by not less than 1/2-inch (12.7 mm) gypsum board applied to the garage side.
Planning Review Approved 05/26/2022 05/19/2022
Michael Fitz ((970) 879-2704)   Send Email
Miscellaneous
Resolved
05/19/2022


Property is skylined and a balloon test will be needed to determine compliance with skyline regulations.
Skyline test passed.

Fees

Paid Fees Amount Paid Owing Date Paid
Routt County Planning Dept Plan Review Fee $75.00 $75.00 Paid 04/19/2022
Routt County Use Tax Fee $1,818.27 $1,818.27 Paid 05/27/2022
Building Permit Fee $1,932.62 $1,932.62 Paid 05/27/2022
Plan Review Fee $1,256.20 $1,256.20 Paid 04/19/2022
Returned Payment/NSF fee $20.00 $20.00 Paid 05/27/2022
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00

Inspections

Inspection Outcome Requested Scheduled Date Inspected
Roofing Inspection Pending
Grading Inspection Pending
Mike Mordi   Send Email
Final Grading Inspection Pending
Tony Brown ((970) 870-5344)   Send Email
Building Final Inspection Pending
Structural Inspection Pending
Drywall Inspection Pending
Framing Inspection Pending
Miscellaneous
Outstanding
05/13/2024
1. Get as built drawings approved for changing vaulted part of ceiling over living room to storage and using 2x6 framing instead of 2x6 LSL

Footing Inspection Passed 9/28/2022 9/28/2022 09/28/2022
Silas Ebbert ((970) 870-5347)   Send Email
Foundation Inspection Passed 11/4/2022 11/4/2022 11/04/2022
Silas Ebbert ((970) 870-5347)   Send Email
Foundation Drain Inspection Partial Pass 11/28/2022 11/28/2022 11/28/2022
Ron Norton ((970) 870-5331)   Send Email
Foundation Drain Inspection Passed 5/26/2023 5/26/2023 05/26/2023
Silas Ebbert ((970) 870-5347)   Send Email
Framing Inspection Partial Pass 7/12/2023 7/12/2023 07/12/2023
Ron Norton ((970) 870-5331)   Send Email
Framing Inspection Not Ready 10/6/2023 10/6/2023 10/06/2023
Jeff Yeiser ((970) 870-5371)   Send Email
Insulation Inspection Partial Pass 12/12/2023 12/12/2023 12/12/2023
Ron Norton ((970) 870-5331)   Send Email
Insulation Inspection Partial Pass 1/5/2024 1/5/2024 01/05/2024
Silas Ebbert ((970) 870-5347)   Send Email
Insulation Inspection Passed 3/7/2024 3/7/2024 03/07/2024
Ron Norton ((970) 870-5331)   Send Email
Drywall Inspection Partial Pass 5/13/2024 5/13/2024 05/13/2024
Silas Ebbert ((970) 870-5347)   Send Email
Framing Inspection Partial Pass 5/13/2024 5/13/2024 05/13/2024
Silas Ebbert ((970) 870-5347)   Send Email
Miscellaneous
Carried Forward
05/13/2024
1. Get as built drawings approved for changing vaulted part of ceiling over living room to storage and using 2x6 framing instead of 2x6 LSL

Conditions

Condition Status Department Category Expiration Date Due Date
Design Engineer on-site Wastewater final report Open Environmental Health Prior to Issuance of TCO/CO/CC
: Design Engineer on-site Wastewater final report, including as Built plans.
Blower door test results Open Prior to Final Building Inspection
: Deferred Blower Door Test Certificate of Compliance: The building or dwelling unit (except within the Town of Hayden) must complete a Blower Door Test with a passing score of Equal/Less than 3 air changes per hour (3ACH), this certificate must be present for our Inspectors prior to approval of a Temporary Certificate of Occupancy/ Certificate of Occupancy. Please also upload this Blower Door Certificate to the Building Department Permit Record

Related Permit & Planning Applications

Reference Number Status Type
PRPL230587 Permit(s) Issued Plumbing
PRMH230588 Permit(s) Issued Mechanical
PREL240335 Permit(s) Issued Electrical

Documents & Images

Date Uploaded File Type Name
04/19/2022 SobeskiShop_ResCheck Report_22013
05/20/2022 Plans ArchitecturalPlans_SobeskiShop_22013 (Received) (Stamped)
04/19/2022 Report 21-12307 Sobeski OWTS Design Report
05/20/2022 Report 21-12307 Sobeski S&FI Report (Stamped)
05/20/2022 Plans 93759 JAYME SOBESKI PERMIT STAMPED (Received) (Stamped)
05/20/2022 Plans StructuralPlans_SobeskiShop_22013 (Received) (Stamped)
04/19/2022 Receipt Receipt for transaction:2022-000284
05/02/2022 Letter Permit Review Corrections Notice (Generate/Send Correction Notice)
05/20/2022 Revision 1-SitePlan_Sobeski Shop_22013 (Stamped)
05/17/2022 Letter Permit Review Corrections Notice (Generate/Send Correction Notice)
05/20/2022 Letter Permit - Detailed
05/20/2022 Receipt Receipt for transaction:2022-000452
05/20/2022 Permit Permit - Detailed
05/27/2022 Receipt Receipt for transaction: 2022-000505
09/28/2022 Report Inspection Report (Footing Inspection)
10/24/2022 Revision2Full_Sobeski Shop_22013 (Stamped)
11/04/2022 Report Inspection Report (Foundation Inspection)
11/28/2022 Report Inspection Report (Foundation Drain Inspection)
05/26/2023 Report Inspection Report (Foundation Drain Inspection)
07/12/2023 Report Inspection Report (Framing Inspection)
09/19/2023 1-STEEL bolt test
10/06/2023 Report Inspection Report (Framing Inspection)
12/12/2023 Report Inspection Report (Insulation Inspection)
01/05/2024 Report Inspection Report (Insulation Inspection)
03/07/2024 Report Inspection Report (Insulation Inspection)
05/13/2024 Report Inspection Report (Drywall Inspection)
05/13/2024 Report Inspection Report (Framing Inspection)