Permit Application Status

PRPF221773


You will only be able to schedule inspections if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRPF221773
Manufactured/Factory Built Building
Closed
JONES, STEPHEN & BAXTER, AMY (JT)
New
R-3 - Residential, one- and two-family
Factory built 572 sq ft home on 20 acre parcel
12/08/2022
03/16/2023
03/16/2026
03/10/2025

Locations

Submittals

1 Permit Application Submittal 12/08/2022      Status: Returned for Correction
Review Type Outcome Est. Completion Date Completed
Public Works Review Failed 01/11/2023 01/09/2023
Building Code Review Failed 01/11/2023 01/05/2023
GIS Land Development Review Approved 01/11/2023 01/05/2023
Planning Review Approved 01/11/2023 01/04/2023
Environmental Health Review Failed 01/11/2023 12/29/2022
Fire Code Review Failed 01/11/2023 12/28/2022

2 Permit Application Submittal 01/10/2023      Status: Pending
Review Type Outcome Est. Completion Date Completed
COO Review - Environmental Health Approved 03/14/2025 03/07/2025
COO Review - Building Code Approved 10/23/2024 10/16/2024
COO Review - Environmental Health Failed 10/15/2024 10/15/2024
COO Review - Building Code Failed 10/17/2023 10/17/2023
COO Review - Building Code Failed 09/06/2023 09/06/2023
COO Review - Public Works Approved 09/06/2023 09/05/2023
COO Review - Environmental Health Failed 09/06/2023 08/29/2023
Fire Code Review Approved 02/20/2023 02/22/2023
Public Works Review Approved 02/20/2023 02/21/2023
Building Code Review Approved 02/20/2023 02/13/2023
Environmental Health Review Approved 02/20/2023 02/13/2023

Fees

There are no fees for this permit application, or you are not authorized to view them.

Inspections

Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection Partial Pass 4/12/2023 4/12/2023 04/12/2023
Jeff Yeiser ((970) 870-5371)   Send Email
Foundation Inspection Passed 4/24/2023 4/24/2023 04/24/2023
Jeff Yeiser ((970) 870-5371)   Send Email
Foundation Drain Inspection Passed 5/5/2023 5/5/2023 05/05/2023
Jeff Yeiser ((970) 870-5371)   Send Email
Foundation Water Proofing Passed 5/5/2023 5/5/2023 05/05/2023
Jeff Yeiser ((970) 870-5371)   Send Email
Foundation/Underslab Insulation Passed 5/5/2023 5/5/2023 05/05/2023
Jeff Yeiser ((970) 870-5371)   Send Email
Framing Inspection Partial Pass 7/11/2023 7/11/2023 07/11/2023
Jeff Yeiser ((970) 870-5371)   Send Email
Building Final Inspection Partial Pass 8/29/2023 8/29/2023 08/29/2023
Jeff Yeiser ((970) 870-5371)   Send Email
Lath/Veneer Inspection VOID 08/29/2023
Heidi Spengler ((970) 870-5332)   Send Email
Radon Piping VOID 08/29/2023
Heidi Spengler ((970) 870-5332)   Send Email
Wall/Roof Sheeting VOID 08/29/2023
Heidi Spengler ((970) 870-5332)   Send Email
Footing Inspection VOID 08/29/2023
Heidi Spengler ((970) 870-5332)   Send Email
Framing Inspection VOID 08/29/2023
Heidi Spengler ((970) 870-5332)   Send Email
Drywall Inspection VOID 08/29/2023
Heidi Spengler ((970) 870-5332)   Send Email
Final Grading Inspection Passed 09/05/2023
Tony Brown ((970) 870-5344)   Send Email
Building Final Inspection Partial Pass 10/10/2023 10/10/2023 10/10/2023
Jeff Yeiser ((970) 870-5371)   Send Email
Building Final Inspection Failed 6/27/2024 6/27/2024 06/27/2024
Todd Carr ((970) 870-5330)   Send Email
Building Final Inspection Passed 10/8/2024 10/8/2024 10/08/2024
Todd Carr ((970) 870-5330)   Send Email

Conditions

Condition Status Category
Design Engineer on-site Wastewater final report Resolved Prior to Issuance of TCO/CO/CC
Environmental Health
Design Engineer on-site Wastewater final report, including as Built plans received 3/6/2025 [Christopher Peters @ 03/07/2025 11:25 AM]
Heat Loss Calculations Deferred Submittal Resolved Prior to Mechanical Permit Issuance for Heat
Building Services
Heal Load Calculations must be submitted, heat pump equipment specs to verify is for cold climate, Manual J is used for sizing and stated size is reviewed and approved prior to any heating equipment being installed.
Blower door test results Resolved Prior to Issuance of CO/CC
Building Services
Blower Door Test Results of 5.0ACH or better per DOLA Code

Related Permit & Planning Applications

Reference Number Status Type
PRSP221757 Closed On-Site Wastewater
PREL230646 Closed Electrical
PRPL230755 Closed Plumbing

Documents & Images

Date Uploaded File Type Name
12/08/2022 Report Soil Report 28395 Yellow Jacket 12-3-22
12/09/2022 Letter Incomplete Application Notice (Generate/Send Incomplete Application Notice)
01/05/2023 Letter NewAddressNotification_Jones_Baxter_01052023
01/10/2023 Letter Permit Review Corrections Notice (Generate/Send Correction Notice)
01/10/2023 Plans State Approved Plans for Manufactured-Factory Built Buildings 28395 Yellow Jacket 12-3-22 copy (Received)
01/10/2023 Form PRPF221773 INST AUTH FORM (Received)
01/10/2023 Form PRPF221773 Prop Own Form (Received)
01/10/2023 Plans Architectural Plans 28395 Yellow Jacket 12-3-22 (Received)
02/10/2023 Daikin_2mx18axvju-submittal_Heat Pump
02/10/2023 Osburn 1700 Install Manual_45982a_2021-05-06
02/23/2023 Plans Structural Calculations UPDATED 28395 Yellow Jacket 01-31-23 (Received)
02/23/2023 Plans Site Plan 28305 Yellow Jacket 2-10-23 (Received) (Stamped)
02/23/2023 Plans Structural Plans UPDATED 28395 Yellow Jacket 02-01-23 (Received) (Stamped)
03/16/2023 Letter Permit - Detailed
03/16/2023 Receipt Receipt for transaction:2023-000179
04/12/2023 Report Inspection Report (Footing Inspection)
04/24/2023 Report Inspection Report (Foundation Inspection)
05/05/2023 Report Inspection Report (Foundation Drain Inspection)
05/05/2023 Report Inspection Report (Foundation/Underslab Insulation)
05/05/2023 Report Inspection Report (Foundation Water Proofing)
07/11/2023 Report Inspection Report (Framing Inspection)
08/29/2023 Report Inspection Report (Building Final Inspection)
10/10/2023 Report Inspection Report (Building Final Inspection)
10/20/2023 Report Daikin_2mx18axvju-submittal_Heat Pump (1)
06/27/2024 Report Inspection Report (Building Final Inspection)
06/27/2024 Report 2015 IECC Air-leakage Test - 28305 Yellow Jacket Dr
08/20/2024 IECC_Air-leakage Tests_28305 Yellow Jacket Dr-2
03/10/2025 Letter Certificate of Occupancy