CityView Portal

Permit Application Status

PRPF231763


You will only be able to schedule inspections if you are a contact on the permit application.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRPF231763
Manufactured/Factory Built Building
Permit(s) Issued
CAMILLETTI & SONS, INC.
New
U - Utility, miscellaneous
Construction of Town of Milner wastewater treatment plant including site-built, below-ground tanks that also serve as the foundation for placement of factory-built, modular, containerized treatment facility on top of tanks.
12/27/2023
04/23/2024

Locations

Submittals

1 Permit Application Submittal 12/27/2023      Status: Returned for Correction
Review Type Outcome Est. Completion Date Completed
Public Works Review Approved 02/23/2024 02/29/2024
Electrical Review Approved 02/23/2024 02/23/2024
External Agencies Review Approved 02/23/2024 02/22/2024
Building Code Review Failed 02/23/2024 02/16/2024
Environmental Health Review Approved 02/23/2024 02/16/2024
Fire Code Review Approved 02/23/2024 01/24/2024
GIS Land Development Review Approved 02/23/2024 01/05/2024
Planning Review Failed 02/23/2024 01/04/2024

2 Permit Application Submittal 03/01/2024      Status: Pending
Review Type Outcome Est. Completion Date Completed
Building Code Review Approved 10/17/2024 10/10/2024
Building Code Review Failed 05/10/2024 05/07/2024
Building Code Review Approved 04/24/2024 04/19/2024
Planning Review Approved 04/24/2024 04/17/2024

Fees

There are no fees for this permit application, or you are not authorized to view them.

Inspections

Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection Pending
Foundation Drain Inspection Pending
Foundation Water Proofing Pending
Foundation/Underslab Insulation Pending
Wall/Roof Sheeting Pending
Radon Piping Pending
Drywall Inspection Pending
Final Grading Inspection Pending
Tony Brown ((970) 870-5344)   Send Email
Lath/Veneer Inspection Pending
Building Final Inspection Pending
Framing Inspection Pending
Foundation Inspection Partial Pass 5/7/2024 5/7/2024 05/07/2024
Silas Ebbert ((970) 870-5347)   Send Email
Foundation Inspection Partial Pass 5/15/2024 5/16/2024 05/16/2024
Silas Ebbert ((970) 870-5347)   Send Email
Foundation Inspection Partial Pass 6/24/2024 6/24/2024 06/24/2024
Silas Ebbert ((970) 870-5347)   Send Email
Foundation Inspection Passed 7/10/2024 7/10/2024 07/10/2024
Silas Ebbert ((970) 870-5347)   Send Email
Framing Inspection Passed 3/5/2025 3/5/2025 03/05/2025
Ron Norton ((970) 870-5331)   Send Email
Framing Inspection Partial Pass 3/12/2025 3/11/2025 03/12/2025
Todd Carr ((970) 870-5330)   Send Email

Conditions

Condition Status Category
Building Department Conditions to be Completed Resolved Prior to Rough Building Wall Inspections
Building Services
These items and any subsequent review questions will need to be addressed prior to the Building Permit being issued: While the structural calculations submitted indicates anchor types and diameter for lid embeds at container legs, RCRBD inspectors will need the plans to specify fastening design data such as field weld [Ted Allen @ 04/19/2024 1:22 PM] [Ted Allen @ 10/10/2024 11:31 AM]
Miscellaneous Resolved Prior to Rough Building Wall Inspections
Building Services
Make sure fees have been paid.
Certified Survey of Foundation Open Prior to Issuance of TCO/CO/CC
A foundation only building permit will initially be signed off on by Planning. Prior to Planning signing off on the full building permit, a certified survey of the location of the foundation forms must be submitted.

Related Permit & Planning Applications

Reference Number Status Type
PREL240741 Permit(s) Issued Electrical

Documents & Images

Date Uploaded File Type Name
12/27/2023 PermitSummaryMilner_Letter_2023_12_27
12/27/2023 Photograph 20211109_145634549_iOS
12/27/2023 newterra Enclosures Standards
12/27/2023 Report Soils Report
12/27/2023 Plans Milner WWTP Electrical Drawings
12/29/2023 Receipt Receipt for transaction:2023-001721
03/01/2024 Letter Permit Review Corrections Notice (Generate/Send Correction Notice)
03/01/2024 Plans Milner WWTP General Civil Process Drawings (Received)
03/01/2024 Plans Final Calculations - Milner WWTP 11_13_23 (Received)
04/17/2024 PermitSummaryMilner_Letter_2024_04_17
04/22/2024 Form Foundation Only Permits Policy Form_MilnerWWTP_PRPF231763 (Received) (Stamped)
04/23/2024 Permit Permit - Detailed (Generate/Issue Permit(s) - Building)
05/02/2024 PermitSummaryMilner_ResubmittalLetter_2024_05_02
05/02/2024 Plans DensDeck_Prime_Spec
05/02/2024 Plans 2024-03-01 Milner WWTP (Structural Drawings)-Stamped
05/02/2024 Plans 2024-04-16 Milner - Screen Building (Dwgs)-Stamped
05/02/2024 Plans 2024-03-01 Milner WWTP (Structural Calculations)-Stamped
05/02/2024 Plans 2024-04-12 Milner Screen Building (Calcs)-Stamped
05/07/2024 Report Inspection Report (Foundation Inspection)
05/15/2024 Receipt Receipt for transaction:2024-000513
05/16/2024 Report Inspection Report (Foundation Inspection)
06/24/2024 Report Inspection Report (Foundation Inspection)
07/10/2024 Report Inspection Report (Foundation Inspection)
10/09/2024 Form DOLA Permit_NR-0006271 specs
10/09/2024 Plans DOLA Permit_NR-0006271 specs
10/09/2024 Plans DOLA Approved Planset_NR-0006271
10/10/2024 PermitSummaryMilner_ResubmittalLetter_2024_05_02 (Stamped)
10/10/2024 Report Milner Heat Calc Package (Stamped)
10/10/2024 Plans Milner Weld Calcs (Stamped)
10/10/2024 Plans Full_Milner WWTP Structural Drawings_Oct2024 (Stamped)
03/05/2025 Report Inspection Report (Framing Inspection)
03/12/2025 Report Inspection Report (Framing Inspection)